Project Status & Planning Context
November 23, 2026
We asked Linn Creek to bring 515 acres of our land into the city
A new, smaller annexation request, filed with the City on November 20.
By Blake Hodits, MO Lake Development
On Friday, November 20, we filed a new request with the City of Linn Creek. It asks the City to bring about 515 acres of our land inside the city limits. This is called annexation.
- This request is smaller. Our request in September was about 1,931 acres.
- It does not include any of our land along the big power lines.
- The land would come in as agricultural use. Any change would need public notice, a public hearing and a vote of the Board of Aldermen.
- Annexation moves a city line. It does not approve any building.
Our goal is the same as it has always been: a community where people can live, work and enjoy the Lake throughout the year. We are still years away from building.
What happens next
Filing a request does not make it happen. Nothing has been decided.

The full steps, in words
- We filed the request on November 20, 2026.
- The City publishes a notice in the newspaper at least 7 days before the hearing.
- The City holds a public hearing, 14 to 60 days after the request. We expect mid-December. Anyone can speak.
- For 14 days after the hearing, Linn Creek's registered voters can object in writing to the City.
- If fewer than 5% object, the Board of Aldermen votes. If the Board finds the request is reasonable and the City can serve the land, it can bring the land in by ordinance.
- If 5% or more object, state law adds steps. The City writes a plan for serving the land and how it would be zoned, and holds a second public hearing with newspaper notice three weeks in a row. The Board votes, a judge must approve it, and Linn Creek holds an election. More than half of the votes cast in Linn Creek must be yes. Voters living on the land, if any, vote separately.
Source: Missouri law, section 71.012 and section 71.015. The law also lets two voters who live on the land object, if two live there. This is a plain-language summary, not legal advice.