Project Status

Where things stand today.

What is planned, what is signed, and what still needs public review.

Public records checked October 31, 2026

Stage

In planning

No building has started. Plans are developing, and each phase still needs engineering and public approvals.

See Phase 1
Our position

No data center

We moved forward with the purchase of the land with a clear understanding that a data center was not possible, and we are not requesting approval for one. Our objective is to build a community.

Read the full answer
Linn Creek

Withdrawn Oct 14

We withdrew our annexation request on October 14, 2026 to give the City time to put clearer data-center rules in place. As of October 31, 2026, no new hearing date had been announced.

Read the October 15 report
City Agreement

Signed July 27

Ordinance 26-005 sets the rules for new roads, water, and sewer. Joining the city and zoning take separate votes.

See how financing works

Our Community Plan

A plan for year‑round
life at the Lake.

LIVARA is a year-round community planned between Camdenton and Linn Creek, with more than 500 homes envisioned in Phase 1. The vision brings homes, local shops, places to work, open woods, and trails into one plan.

Planning goals, signed agreements, and building permits are three separate steps. Each phase needs full engineering, water and road plans, and public approvals before any building can begin.

MO Lake Development pays for all infrastructure upfront. Any later reimbursement is limited to eligible costs and depends on the agreements' conditions and available revenue; full repayment is not guaranteed. How the agreements work →

A meadow and woodland seen from above, with a small pond beside the trees.
Meadows, ponds, and Ozark woods between Camdenton and Linn Creek.

Project Timeline

Key dates and public records.

Every entry below lists the date, what happened, and a link to the news report or public office.

  1. Annexation request

    Linn Creek annexation request withdrawn

    MO Lake Development withdrew its annexation request on October 14, 2026 to give the City time to put clearer data-center rules in place. We plan to ask again. As of October 31, 2026, no new hearing date had been announced.

    KRMS report, October 15, 2026 →

    Reported October 15. Stepping back from this request does not change the July 27 agreement.

  2. No data center

    No data center in LIVARA

    Blake Hodits shared publicly that LIVARA is moving forward without a data center. We are not building a data center or asking for approval to build one.

    LakeExpo report, September 25, 2026 →

    News report on the announcement. The September meeting date in that article has passed.

  3. Signed agreement

    Linn Creek road and water agreement signed

    The City and MO Lake Development signed a Public Improvement Agreement. Ordinance 26-005 approves this agreement only. It does not annex or rezone the land.

    City of Linn Creek: official notices and City Hall contact →

    Record: Ordinance 26-005 and agreement, July 27, 2026. Contact City Hall for the official file.

Official Sources

Check the public record.

Official city and county notices set all hearing dates, places, and topics. Always call City Hall to confirm details before a meeting.

Official Record · 01

City of Linn Creek

Ask City Hall for Ordinance 26-005 and the July 27, 2026 Public Improvement Agreement. The City website lists current notices and phone numbers.

Linn Creek website and City Hall contact →

Planning Notes & Background

How the project evolved since spring 2026.

This is our first website launch. Below are our spring and fall 2026 planning notes paired with today's facts so neighbors can see what changed.